CAP1835 Road Reconstruction Improvements
Contractor: Hard Rock Concrete, Inc.
Woodland Avenue - Webster Road to Glenwood Road
The contractor will begin pavement removals along the east side of Woodland Avenue starting the week of April 16th. Driveway approaches will also be removed along the east side of the road and back-filled with stone to allow vehicle access. Additionally, six trees will be removed throughout the week. Replacement trees will be planted at the end of the project.
Once the pavement is removed, the new water main will be installed along the east side of the roadway. Residents will be notified of scheduled water shutoffs with a door hanger, though there are no shutoffs planned for the next couple weeks.
Bonnie View Drive - Lloyd Avenue to Northwood Boulevard
The contractor will begin pavement removals along the east side of Woodland Avenue starting the week of April 16. After the pavement is removed, the contractor will begin preparing the road base for paving operations. Residents will be notified via door hanger when driveway approaches will no longer be available.
Yorba Linda Boulevard - Fairlawn Avenue to Springer Avenue
No work yet.
Parkway Drive - Normandy Road to Woodward Avenue
No work yet.
Linwood Avenue - Webster Road to Glenwood Road
No work to begin until school is out for the summer.
Delaware Avenue - E. Kenilworth Avenue to E. Harrison Avenue
No work yet.