CAP1735 Road Reconstruction Improvements
Contractor: Mark Anthony Contracting, Inc.
Batavia Avenue
The contractor plans to finish installing the water main piping the week of June 12th. The new water main is scheduled to be chlorinated and tested for the remainder of the week.
A section of sanitary sewer will be replaced between Lincoln Avenue and E. Hudson Avenue.
Dallas Avenue
The contractor plans to begin mobilizing to Dallas Avenue during the week of June 12th and is tentatively scheduled to begin water main installation later in the week.
Fairview Avenue
The contractor is planning to begin work on Fairview Avenue the week of June 12th. The contractor will begin removing concrete and replacing sewer piping within the cul-de-sac area. The concrete within the roadway will also be removed.
The driveways off of Fairview Avenue will be closed during construction. Residents on the south side of Fairview Avenue have been authorized to park in visitor parking spaces at the apartment complex.
The business plaza on the north side of Fairview Avenue will have a temporary gravel driveway installed at the south end of the property during construction as shown below.