CAP1630 Special Assessment Paving Improvements
Contractor: Mark Anthony Contracting, Inc.
Public Alley - East of Rochester Road, from Whitcomb Ave. to Millard Ave.
The contractor has started grading and paving work within the public alley. The alley is scheduled to be paved the week of June 5th.
Bassett Road
The road pavement, driveway approaches and sidewalks have been installed. The contractor plans to perform sod restoration the week of June 5th, weather permitting.
Girard Road
Girard Road has been paved and is open to local traffic only. Driveways and sidewalk work is expected to be completed the week of June 5th. Sod restoration work is planned to occur in the next few weeks.
S. Edison Avenue
Water main work on S. Edison Avenue is complete. The contractor plans to begin preparing the roadway for paving operations during the week of June 5th and plans to pave the road the week of June 12th.Wrenford Road
Restoration work has been pushed back to the week of June 5th.
Massoit Road
Restoration work has been pushed back to the week of June 5th.
W. Park Avenue
The contractor is finishing the connections of individual water services to the new water main. The final water main connection is scheduled for the week of June 5th. Properties that will be without water during water main connections will be notified via door hanger the day beforehand. Shutdowns are typically 4 to 8 hours long.
Paving preparation work is tentatively scheduled for the week of June 12th.Public Alley - 14 Mile Road to Rochester Road (behind businesses)
The contractor is tentatively planning to begin work within the alley towards the end of June.