CAP2410 Water Main Improvements
All water main installation and connections are complete for both streets, only roadwork is remaining.
On Northwood & Sycamore, the contractor will be paving the final layer of asphalt this week once they finish adjusting all the sewer structures. Paving is tentatively scheduled for Wednesday thru Saturday.
The contractor will also be working on cleanup, and landscape restoration this week.