CAP2416/2415 Asphalt Resurfacing
This project will resurface several streets in the residential neighborhoods and the downtown.
CAP2416 Downtown Phase 1
Paving is now complete on the project streets downtown. Only some minor restoration and punch list work still needs to occur.
CAP2415 Neighborhoods
Phase 2: Landscape and irrigation restoration will begin.
Phase 3: The contractor will be milling (removing) the existing roadways. Streets will be posted with 'No Parking' signs 24 hours in advance. Paving to follow next week.
Phase 4: The contractor will be milling (removing) the existing roadways. Streets will be posted with 'No Parking' signs 24 hours in advance. Paving to follow next week.
Phase 5: Crews will be doing concrete work on the east side of Irving working south to north.