CAP2435 Road Reconstruction
This project will completely reconstruct several roads in the city. The table below shows the streets that will be reconstructed this year and the full project map linked above shows the project streets in green. New water main will also be installed on Parkview and Vinsetta.
On Albert Avenue, the contractor will continue to complete the prep work for new road pavement and tentatively plans to pour the new concrete roadway later this week.
On Samoset, both east and west sections were poured last Friday and the roadway will remain closed for at least a week while the new concrete cures and gains strength.
On Parkview, the contractor is working on water services and water main connections this week.
On Vinsetta, the new water main will be undergoing testing this week.
On Nakota, the contractor has begun removing the existing pavement. The crew plans to install new edge drain and finish all the grading by the end of the week.
*As part of this project the contractor will also be installing traffic calming chicanes on Marais Avenue between Thistle and Lexington as approved by the city commission.